BWTS Installation

Customer: Carnival Cruise Lines
Vessel: Carnival Sensation

Project duration: 28 days, in-service
Project description: Installation of AlfaLaval Pure Ballast USGC 3.1 Ballast Water Treatment Systems, including engineering for LR approval and Workshop Drawings. Fabrication and installation of foundations, equipment positioning, piping works (GRE & pressfit), electrical works and automation agreements.

Work was executed during in-service operation. Project commissioned and LR approved on January 20, 2020.

Filtrex together with BF Pump

CIP unit pressfitt connection

UV Reactor

CIP (cleaning in Place) Unit

General look of Equipment Room

General look of Equipment Room with Flowmeter on top

Ballast Pump tie-in points

New Overboard Spools with backflush and stripping connections

BACK
Privacy Settings
We use cookies to enhance your experience while using our website. If you are using our Services via a browser you can restrict, block or remove cookies through your web browser settings. We also use content and scripts from third parties that may use tracking technologies. You can selectively provide your consent below to allow such third party embeds. For complete information about the cookies we use, data we collect and how we process them, please check our Privacy Policy
Youtube
Consent to display content from - Youtube
Vimeo
Consent to display content from - Vimeo
Google Maps
Consent to display content from - Google